According to engineers working on the project, the diversion of traffic onto the bridges will allow for work on other parts of the Kwame Nkrumah interchange.
The project which started two years ago has forced the contractor, Queiroz Galvao Construction, to create a number of diversions and relocations to ease the traffic that builds up at the busy area.
|
Urban Roads Director, Raymond Ahwollu, said the opening of parts of the road were preceded by a short inspection of ongoing works by the president.
Mr Gatsiko said work on the third interchange, which will link Ring Road Central to Ring Road West, was far advanced.
|
He said the outstanding major work is the improvement of the other roads around the Kwame Nkrumah Circle.
Generally, Mr Gatsiko said, the whole project is about 75 percent complete, and indicated that work would be completed by December, 2015, or latest January, 2016.
The opening of the road generated some controversy when the bridges were draped in party colours of the governing National Democratic Congress.
Source: Adom Online